周建成, 朱振兴, 闫熠. 水平摆倾斜仪配电系统的改造[J]. 华北地震科学, 1999, 17(3): 48-49,60.
引用本文: 周建成, 朱振兴, 闫熠. 水平摆倾斜仪配电系统的改造[J]. 华北地震科学, 1999, 17(3): 48-49,60.
Zhou Jiancheng, Zhu Zhenxing, Yan Yi. THE REFORM OF POWER DISTRIBUTION SYSTEM OF HORIZONTAL PENDULUM TILTMETER[J]. North China Earthquake Sciences, 1999, 17(3): 48-49,60.
Citation: Zhou Jiancheng, Zhu Zhenxing, Yan Yi. THE REFORM OF POWER DISTRIBUTION SYSTEM OF HORIZONTAL PENDULUM TILTMETER[J]. North China Earthquake Sciences, 1999, 17(3): 48-49,60.

水平摆倾斜仪配电系统的改造

THE REFORM OF POWER DISTRIBUTION SYSTEM OF HORIZONTAL PENDULUM TILTMETER

  • 摘要: 水平摆倾斜仪配电系统在洞内放置,因洞内潮湿,仪器零部件锈蚀严重,经常发生故障,严重影响资料的连续率。本文提出将配电盘移出山洞,到办公室工作,通过计算和试验,完成了对赤城地震台的线路改造。仪器运行两年来,情况良好,彻底解决了十几年来一直困扰赤城台倾斜仪故障频繁的问题。

     

    Abstract: The power distribution system laid inside the cave often has broken down due to moisture inside the cave and serious rust of the instrument parts,which seriously affects the continuous rate of the data.In this paper,it has been proposed that the distributor is moved from the cave to the office,the reform of the power distribution system of Chicken Seismological Station has been fulfiled by calculation and test.Since the reform,the instrument has been running well for two years.The problem which made the tiltmeter had frequent trubles for more that ten years has been completely solved.

     

/